Country Club Drive at Sharon Valley Road Roundabout


The purpose of this project is to install a single-lane modern roundabout at the Country Club Drive and Sharon Valley Road intersection to improve safety and capacity. When the roundabout is constructed, left turns from Kind Road to Sharon Valley Road will be prohibited in order to improve safety and capacity at that intersection. Those movements will be made by turning right from King Road, and then making a u-turn movement at the new roundabout, in order to proceed eastbound on Sharon Valley Road.

Click here for preliminary layout.

Construction Begins: Summer 2021
Duration: 3 Months
Construction Administrator: City of Newark
Estimated Cost: $1.1 Million
Funding: OPWC, City of Newark