West Church Street Improvements


The project location is West Church Street between North 30th Street and Dietrich Street.
The project is an extension of the previous project completed west of North 29th Street, and will provide: 

  • New curb and gutter to convey stormwater runoff
  • New sidewalk on both sides of the street for pedestrian safety
  • New pavement with a center turn lane to improve safety for turning motorists

Construction Begins: 2023
Duration: 6 Months
Construction Administrator: ODOT
Estimated Cost: $2 Million
Funding: ODOT, City of Newark